FOCUS TOWER MOUNTAIN

Complete minimum C$2.0M financing: 

        Phase One Drilling Program

               Eastern Intrusive Contact incl. the P target (6.0 g/t Au)

               1,800 m strike length

               200 m section lines with 2 holes (500 m) per section)

               Target 100 and 200 m from surface

               Est. metres = 5,000 (est. 3-4 months)

Complete minimum C$5.0M financing: 

        Phase Two Drilling Program

               Northern and Southern Intrusive Contact

               Select in-fill drilling along Eastern Contact, if warranted

               3,600 m strike length

               200 m section lines w 2 holes (500 m) per section)

               Target 100 and 200 m from surface

               Est. metres = 10,000 (est. 3-6 months)

Initiate NI 43-101 Mineral Resource Estimate